๐Project Closed๐ง Addition / Renovation๐ต This project involves public funds, public land, or is a Federally funded roadway project.
KELTON ISD ENCLOSED WALKWAY - 2008 IMPRO
16703 FM 2697, Wheeler, TX 79096, Wheeler, TX, 79096
Completed100%
๐Project Metrics
TDLR #EABPRJA9802347$175K
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Oct 11, 2008
Start:Oct 1, 2008
Target:Dec 1, 2008
๐
Project Closed
Project has been completed and closed
๐Scope of Work
NEW COVERED WALKWAY BETWEEN TWO EXISTING BUILDINGS
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 11, 2008
Construction Start
October 1, 2008
Expected Completion
December 1, 2008
๐Related Projects
๐คSame Owner
$2.9M totalProperty Owner
Design Firm
๐๏ธ
GRIMES & ASSOCIATES
4 projects ยท $15.0M
MR ALBERT R. MOFFITT PO BOX 65, 21103 FM 179, WOLFFORTH, TX 79382