DCCD- RICHLAND COLLEGE(ELEVATOR REMODEL)

12800 ABRAMS RD, Dallas, TX 75243, Dallas, TX, 75243
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2809061
$250K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Mar 7, 2012
Start:Jun 1, 2012
Target:Sep 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Replacing existing elevator with new compliant one. Removing walls inside building to create a new hallway to th

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 7, 2012
Construction Start
June 1, 2012
Expected Completion
September 1, 2012