๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

RAD ROOM 3 EQUIP CHANGE

3500 GASTON AVE., Dallas, TX 75246, Dallas, TX, 75246
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2809778
$110K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:Mar 19, 2012
Start:Mar 1, 2012
Target:May 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Selective renovation in an existing radiology room for new equipment with upgraded electrical and mechanical ser

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 19, 2012
Construction Start
March 1, 2012
Expected Completion
May 1, 2012