๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

GALVESTON COUNTY ROAD AND BRIDGE BOLIVAR

950 NOBLE CARL DRIVE, Crystal Beach, TX 77650, Crystal Beach, TX, 77650
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4804187
$1.9M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 7mo
Duration
Registered:Nov 11, 2013
Start:Jan 1, 2014
Target:Jul 31, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

2,800 sf office space and 7,200 sf maintenance and storage warehouse

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 11, 2013
Construction Start
January 1, 2014
Expected Completion
July 31, 2015