โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

LAMAR STREET

LIMITS IH-45 TO EMERY STREET, Dallas, TX 75203, Dallas, TX, 75203
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5811761
$8.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3y 9mo
Duration
Registered:Mar 13, 2015
Start:May 1, 2015
Target:Dec 31, 2018
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Paving, drainage, landscape, and lighting along Lamar Street.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 13, 2015
Construction Start
May 1, 2015
Expected Completion
December 31, 2018