Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6804253
$205K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Nov 6, 2015
Start:Feb 1, 2016
Target:Jul 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

0.8 mile extension of Trail de Paris of both concrete and asphalt trail sections.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 6, 2015
Construction Start
February 1, 2016
Expected Completion