๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

T & P TRAIL EXTENSION

NORTHEAST TEXAS TRAIL, New Boston, TX 75570, New Boston, TX, 75570
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6808193
$482K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Jan 15, 2016
Start:Mar 1, 2016
Target:Jul 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Upgrade of a gravel trail to an stabilized asphalt surface trail.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 15, 2016
Construction Start
March 1, 2016
Expected Completion
July 1, 2016