๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

MID-SOUTH SYNERGY MONTGOMERY COUNTY

15610 FM 2854, Montgomery, TX 77316, Montgomery, TX, 77316
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7801853
$395K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
11 months
Duration
Registered:Sep 30, 2016
Start:Nov 1, 2016
Target:Sep 30, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

new freestanding fuel station w/ toilet and associated vehicle parking

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 30, 2016
Construction Start
November 1, 2016
Expected Completion
September 30, 2017