๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
US 67 WIDENING PROJECT
US 67 - BELT LINE TO IH 20, Dallas, TX 75104, Dallas, TX, 75104
Completed100%
๐Project Metrics
TDLR #EABPRJB7806298$55.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
2y 3mo
Duration
Registered:Dec 8, 2016
Start:Mar 1, 2017
Target:Jun 1, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of Sidewalks, ADA Ramps, Pedestrian SignalElements
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 8, 2016
Construction Start
March 1, 2017
Expected Completion
June 1, 2019
๐Related Projects
Property Owner
๐ค
TXDOT DISTRICT: DALLAS
4 projects ยท $461.8M
JASON MASHELL, P.E. 4777 E. US 80, MESQUITE, TX 75150