๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BEACHSIDE BAY CABANA PROJECT

9001 BOULEVARD 26, North Richland Hills, TX 76180, North Richland Hills, TX, 76180
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7806957
$180K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Dec 16, 2016
Start:Jan 1, 2017
Target:May 1, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of eight 10'x15' cabanas and connecting concrete paths.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 16, 2016
Construction Start
January 1, 2017
Expected Completion
May 1, 2017