โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BOND 2016 PROJECT HVAC-ROOF-ACCESSIBILIT

19200 COBB AVE., Tornillo, TX 79853, Tornillo, TX, 79853
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7810020
$3.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Feb 7, 2017
Start:Mar 1, 2017
Target:Aug 1, 2017
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Replacing roof, installing HVAC roof top system and updating existing school accessibility standards

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 7, 2017
Construction Start
March 1, 2017
Expected Completion