โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

PAVING & DRAINAGE IMPROV FOR EWING AVE.

FROM GENOA AVE TO GALLOWAY AVE, Dallas, TX 75216, Dallas, TX, 75216
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7811463
$1.9M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 9mo
Duration
Registered:Feb 27, 2017
Start:Aug 1, 2017
Target:Apr 10, 2019
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Reconstruction of an existing roadway with the additionof curb and gutter, sidewalks and barrier free ramps at

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 27, 2017
Construction Start
August 1, 2017
Expected Completion
April 10, 2019

Quick Actions

TDLR ID: EABPRJB7811463

Property Owner

๐Ÿ‘ค
CITY OF DALLAS
4 projects ยท $3.6M
WILKENS ENGMANN 1500 MARILLA ST., DALLAS, TX 75201

Design Firm

๐Ÿ›๏ธ
LINA T. RAMEY & ASSOCIATES
LILAH RAMEY, PE 3320 BELT LINE RD., FARMERS BRANCH, TX 75234