๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
DOWLEN ROAD ACP RESURFACE PROJECT
DOWLEN RD, Beaumont, TX 77706, Beaumont, TX, 77706
Completed100%
๐Project Metrics
TDLR #EABPRJB7823946$3.2M
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 5mo
Duration
Registered:Aug 24, 2017
Start:Sep 1, 2017
Target:Jan 24, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of sidewalks, ramps, road
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 24, 2017
Construction Start
September 1, 2017
Expected Completion
January 24, 2019
๐Related Projects
Property Owner
๐ค
CITY OF BEAUMONT
4 projects ยท $16.0M
HAROLD E CROCHET JR 801 MAIN, BEAUMONT, TX 77701