๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

US 62/180 MONTANA AVE WIDENING

MONTANA AVE, El Paso, TX 79925, El Paso, TX, 79925
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8810625
$121.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 years
Duration
Registered:Feb 15, 2018
Start:Sep 1, 2018
Target:Sep 1, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of WB & EB Mainlanes & WBFR from Global Reach to Tierra Este & reconstruction of intersections at G

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 15, 2018
Construction Start
September 1, 2018
Expected Completion
September 1, 2020

Quick Actions

TDLR ID: EABPRJB8810625

Property Owner

๐Ÿ‘ค
TXDOT DISTRICT: EL PASO
4 projects ยท $99.8M
ROBERT BIELEK, P.E., DPA 13301 GATEWAY BLVD WEST, EL PASO, TX 79928

Design Firm

๐Ÿ›๏ธ
DANNENBAUM ENGINEERING
4 projects ยท $170.4M
JOSE L. REYES, P.E. 10737 GATEWAY BLVD W, STE 112, EL PASO, TX 79935

Registered Accessibility Specialist

๐Ÿ“‹
FONSECA, FRANK
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201