๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SOUTHERN SIDEWALK IMPROVEMENTS
ALONG SHADY LANE, Edgewood, TX 75117, Edgewood, TX, 75117
Completed100%
๐Project Metrics
TDLR #EABPRJB8811905$184K
Project Value
โ
Square Feet
โ
Cost/SqFt
6 months
Duration
Registered:Mar 6, 2018
Start:Aug 1, 2018
Target:Feb 1, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Installing about 1,400 linear feet of 6' wide sidewalk along the north and west edge of Shady Lane.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 6, 2018
Construction Start
August 1, 2018
Expected Completion
February 1, 2019
๐Related Projects
๐คSame Owner
$784K total๐๏ธSame Design Firm
$2.4M totalProperty Owner
๐ค
CITY OF EDGEWOOD
2 projects ยท $784K