๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
LAWSON MIDDLE SCHOOL
14000 STANCLIFF ST., Houston, TX 77045, Houston, TX, 77045
Construction50%
๐Project Metrics
TDLR #EABPRJB8815250$13.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
8 months
Duration
Registered:Apr 19, 2018
Start:Jun 1, 2018
Target:Feb 1, 2019
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
ADDITION TO NEW MIDDLE SCHOOL BUILDING OF TWO NON-SIMULTANEOUS CLASSROOMS
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 19, 2018
Construction Start
June 1, 2018
Expected Completion
February 1, 2019
๐Related Projects
๐คSame Owner
$133.4M totalProperty Owner
๐ค
HOUSTON INDEPENDENT SCHOOL DISTRICT
4 projects ยท $133.4M
MEREDITH SMITH 4400 W 18TH ST, HOUSTON, TX 77092
Design Firm
๐๏ธ
HARRISONKORNBERG ARCHITECTS
4 projects ยท $22.3M
DANIEL KORNBERG 3800 BUFFALO SPEEDWAY, HOUSTON, TX 77098