๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
ELECTRIC VEHICLE CHARGING STATION SPRING
102 SAWDUST RD., Spring, TX 77308, Spring, TX, 77308
Completed100%
๐Project Metrics
TDLR #EABPRJB8819926$140K
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Jun 20, 2018
Start:Jul 1, 2018
Target:Sep 1, 2018
๐
Project Closed
Project has been completed and closed
๐Scope of Work
INSTALLATION OF 3 NEW ELECTRIC VEHICLE CHARGING STATIONS, EQUIPMENT PAD AND SWITCHGEAR
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 20, 2018
Construction Start
July 1, 2018
Expected Completion
September 1, 2018