๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

SIMMONS PUMP & SUPPLY TESTING & DISTRIBU

805 28TH STREET, Lubbock, TX 79404, Lubbock, TX, 79404
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB9803043
$2.3M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Oct 15, 2018
Start:Nov 1, 2018
Target:Apr 1, 2019
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New, ground-up construction for a water pump Testing & Distribution Facility with office area. Project includes

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 15, 2018
Construction Start
November 1, 2018
Expected Completion
April 1, 2019