๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
NORTHSHORE DIALYSIS
1810 BILLY G. WEBB., Portland, TX 78374, Portland, TX, 78374
Construction50%
๐Project Metrics
TDLR #EABPRJB9805308$1.2M
Project Value
โ
Square Feet
โ
Cost/SqFt
6 months
Duration
Registered:Nov 15, 2018
Start:Feb 1, 2019
Target:Aug 1, 2019
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Shell and interior buildout for an outpatient kidney dialysis center.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 15, 2018
Construction Start
February 1, 2019
Expected Completion
August 1, 2019
๐Related Projects
๐คSame Owner
$4.8M total๐๏ธSame Design Firm
$4.8M totalProperty Owner
๐ค
GENESIS KC DEVELOPMENT LLC
4 projects ยท $4.8M
DAVID WILSON 2000 16TH STREET, DENVER, CO 80202
Design Firm
๐๏ธ
SIKES GROUP INC.
4 projects ยท $4.8M
HERSCHEL SIKES 12012 WICKCHESTER, SUITE 650, HOUSTON, TX 77079