Fredericksburg 2018 Bond Projects Phase 2
11167 Hwy 16S, Fredericksburg, TX 78624, Fredericksburg, TX, 78624
Completed100%
๐Project Metrics
TDLR #TABS2019000980$250K
Project Value
11,600
Square Feet
$22/sqft
Cost/SqFt
10 months
Duration
Registered:Dec 17, 2018
Start:Jan 1, 2019
Target:Nov 1, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
classroom renovations, new exterior stair and new exterior lift at the High school
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 17, 2018
Construction Start
January 1, 2019
Expected Completion
November 1, 2019