๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Grapevine Fire Station No. 3

3100 Timberline Drive, Grapevine, TX 76051, Grapevine, TX, 76051
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019017625
$6.7M
Project Value
13,713
Square Feet
$492/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Aug 5, 2019
Start:Nov 1, 2019
Target:Dec 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

3 bay fire station with associated sitework

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 5, 2019
Construction Start
November 1, 2019
Expected Completion
December 1, 2020