๐Project Closed๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Tomball Memorial HS Renovations and Additions
19100 Northpointe Ridge Lane, Tomball, TX 77377, Tomball, TX, 77377
Completed100%
๐Project Metrics
TDLR #TABS2020001195$36.1M
Project Value
209,000
Square Feet
$173/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Sep 18, 2019
Start:Jan 6, 2020
Target:Jun 7, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Additions and renovations to provide additional 750 student capacity to the existing facility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 18, 2019
Construction Start
January 6, 2020
Expected Completion
June 7, 2021
๐Related Projects
๐คSame Owner
$54.9M totalProperty Owner
๐ค
Tomball Independent School District
4 projects ยท $54.9M
310 S. Cherry Street, Tomball, Texas 77375