Bloomdale Road Extension
Bloomdale Road from Community Ave to Hardin Rd, Mckinney, TX 75071, Mckinney, TX, 75071
Completed100%
๐Project Metrics
TDLR #TABS2020006830$12.7M
Project Value
579,348
Square Feet
$22/sqft
Cost/SqFt
2y 5mo
Duration
Registered:Dec 6, 2019
Start:Feb 1, 2020
Target:Jul 1, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construction of two lane principal arterial facility.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 6, 2019
Construction Start
February 1, 2020
Expected Completion
July 1, 2022
๐Related Projects
๐คSame Owner
$9.3M totalProperty Owner
Design Firm
๐๏ธ
Burns & McDonnell Engineering Company, Inc.
4 projects ยท $898.3M
15900 N. Dallas Parkway Suite 700, Dallas, Texas 75248