Six Flags World Headquarters

1000 Ballpark Way, Suite 400, Arlington, TX 76011, Arlington, TX, 76011
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020010471
$3.3M
Project Value
45,000
Square Feet
$73/sqft
Cost/SqFt
3 months
Duration
Registered:Jan 31, 2020
Start:Mar 2, 2020
Target:May 29, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Interior demolition and renovation @ Basement and Level 4. New finish applications and updates @ Level 5.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 31, 2020
Construction Start
March 2, 2020
Expected Completion
May 29, 2020