๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

K.N.J. Enterprises

3607 FM 1128, Pearland, TX 77584, Pearland, TX, 77584
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020017388
$1.0M
Project Value
5,084
Square Feet
$197/sqft
Cost/SqFt
11 months
Duration
Registered:May 14, 2020
Start:Sep 1, 2020
Target:Aug 1, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

A ground up construction of a single story 5084 SF building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 14, 2020
Construction Start
September 1, 2020
Expected Completion
August 1, 2021