๐Project Closed๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
BTU - Transformer Containment Building
2301 Fountain Ave - Bldg 211, Bryan, TX 77803, Bryan, TX, 77803
Completed100%
๐Project Metrics
TDLR #TABS2020018826$220K
Project Value
1,100
Square Feet
$200/sqft
Cost/SqFt
3 months
Duration
Registered:Jun 10, 2020
Start:Aug 11, 2020
Target:Nov 11, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Addition of 1100 sf to existing warehouse building, no plumbing, no public access. Storage of hazardous materials - Building fully secure.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 10, 2020
Construction Start
August 11, 2020
Expected Completion
November 11, 2020
๐Related Projects
๐คSame Owner
$5.8M totalProperty Owner
๐ค
Bryan Texas Utilities
Contact: James Bodine
4 projects ยท $5.8M
PO Box 1000, Bryan, Texas 77805
Design Firm
๐๏ธ
williamson group architects
4 projects ยท $16.9M
106 East 26th Street, Bryan, Texas 77803