Holiday Hill Road, Midland, TX 79707, Midland, TX, 79707
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020019240
$14.3M
Project Value
33,325
Square Feet
$430/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Jun 18, 2020
Start:Jul 8, 2020
Target:Aug 10, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

A new Holy Cross Catholic High School.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 18, 2020
Construction Start
July 8, 2020
Expected Completion
August 10, 2021