๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SH 34

from S of Airport Rd to IH 20, Terrell, TX 75160, Terrell, TX, 75160
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021014785
$961K
Project Value
75,000
Square Feet
$13/sqft
Cost/SqFt
1y 9mo
Duration
Registered:May 4, 2021
Start:Dec 1, 2021
Target:Sep 1, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of sidewalks & ADA ramps, Consisting of grading, base, Pavement

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 4, 2021
Construction Start
December 1, 2021
Expected Completion
September 1, 2023