๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
CHARLES SCHWAB DFW3 - PHASE 3
SE CORNER/STATE HWY 114 & 170, Westlake, TX 76092, Westlake, TX, 76092
Completed100%
๐Project Metrics
TDLR #TABS2021015144$15.0M
Project Value
108,000
Square Feet
$139/sqft
Cost/SqFt
9 months
Duration
Registered:May 7, 2021
Start:Aug 2, 2021
Target:May 6, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
INTERIOR FINISH OUT OF LEVELS 1, 2, AND 3 OF EXISTING DFW3 BUILDING
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 7, 2021
Construction Start
August 2, 2021
Expected Completion
May 6, 2022