๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

American Airlines-Terminal C-High C Gate Interior Fit-out

2330 N International Parkway, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021016611
$18.0M
Project Value
110,000
Square Feet
$164/sqft
Cost/SqFt
1y 1mo
Duration
Registered:May 27, 2021
Start:Jun 1, 2021
Target:Jun 30, 2022
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Interior finish-out of ramp level support spaces and concourse level gate spaces for gates 35 through 39

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 27, 2021
Construction Start
June 1, 2021
Expected Completion
June 30, 2022