๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Best Flow #2 Building B
1330 Markum Gate Way, Fort Worth, TX 76126, Fort Worth, TX, 76126
Completed100%
๐Project Metrics
TDLR #TABS2021020340$940K
Project Value
11,920
Square Feet
$79/sqft
Cost/SqFt
6 months
Duration
Registered:Jul 21, 2021
Start:Aug 1, 2021
Target:Feb 1, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New construction of 11920 sf fabrication facility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 21, 2021
Construction Start
August 1, 2021
Expected Completion
February 1, 2022