๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Portable bldg install at Newman Elem. School

12333 Briar Ridge Road, Frisco, TX 75033, Frisco, TX, 75033
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021020800
$50K
Project Value
1,536
Square Feet
$33/sqft
Cost/SqFt
0 months
Duration
Registered:Jul 27, 2021
Start:Aug 2, 2021
Target:Aug 16, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Connect Owner's portable building to utilities and sidewalk

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 27, 2021
Construction Start
August 2, 2021
Expected Completion
August 16, 2021