๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Fannie Mae / Trintech
5600 Granite Pkwy, Plano, TX 75024, Plano, TX, 75024
Completed100%
๐Project Metrics
TDLR #TABS2021021211$850K
Project Value
38,300
Square Feet
$22/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 2, 2021
Start:Aug 15, 2021
Target:Nov 1, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Partial renovation of 2 floors of existing office space to convert to sub-let tenant use. Construction of several fixed offices, updating CEO office, add catering preparation room, include reception area & elevator lobby doors, and other reno work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 2, 2021
Construction Start
August 15, 2021
Expected Completion
November 1, 2021
๐Related Projects
๐คSame Owner
$836K totalProperty Owner
๐ค
Granite Properties
Contact: Carol Borchardt
4 projects ยท $836K
5601 Granite Pkwy #1200, Plano, Texas 75024
Design Firm
Tenant
๐ข
Fannie Mae - George Ashim