โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Trinity Plaza

7101 W Adams, Temple, TX 76502, Temple, TX, 76502
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021021325
$2.0M
Project Value
7,000
Square Feet
$286/sqft
Cost/SqFt
6 months
Duration
Registered:Aug 3, 2021
Start:Oct 1, 2021
Target:Mar 31, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

ground up construction of 7,000 sf gross bldg area retail shell bldg and associated site work for a Phase 1 shopping center on Lot 3 of a newly platted series of parcels at the intersection of Old Waco Rd and West Adams Avenue in Temple, TX.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 3, 2021
Construction Start
October 1, 2021
Expected Completion
March 31, 2022