โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Wichita Falls ISD | WF Memorial High School

6600 Seymour Highway, Wichita Falls, TX 76302, Wichita Falls, TX, 76302
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022001057
$118.1M
Project Value
376,831
Square Feet
$313/sqft
Cost/SqFt
2y 8mo
Duration
Registered:Sep 16, 2021
Start:Oct 25, 2021
Target:May 27, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

A new Wichita Falls Memorial High School for Wichita Falls ISD.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 16, 2021
Construction Start
October 25, 2021
Expected Completion
May 27, 2024