๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Concrete Tiltwall Warehouse
N/A Halff Associates Inc, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Completed100%
๐Project Metrics
TDLR #TABS2022004211$10.1M
Project Value
125,433
Square Feet
$80/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Oct 29, 2021
Start:Jan 17, 2022
Target:Apr 1, 2023
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New Shell Warehouse located in DFW Passport Park.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 29, 2021
Construction Start
January 17, 2022
Expected Completion
April 1, 2023
๐Related Projects
๐คSame Owner
$2.7M totalProperty Owner
๐ค
Stream Realty
Contact: Steve Riordan
4 projects ยท $2.7M
2001 Ross Avenue, Dallas, Texas 75201
Design Firm
๐๏ธ
Halff Associates Inc
4 projects ยท $21.8M
1201 N Bowser Rd Halff Associates Inc, Richardson, Texas 75081