๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Oliver Wyman Office Suite Fit-Out

1717 Main St., 44th Floor, Dallas, TX 75201, Dallas, TX, 75201
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022004719
$1.5M
Project Value
9,120
Square Feet
$164/sqft
Cost/SqFt
3 months
Duration
Registered:Nov 5, 2021
Start:Dec 27, 2021
Target:Mar 22, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Tenant improvements for new office space on a single tenant floor that includes new partitions, ceilings, finishes, mechanical, electrical, plumbing & fire alarm.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 5, 2021
Construction Start
December 27, 2021
Expected Completion
March 22, 2022

Quick Actions

TDLR ID: TABS2022004719

Property Owner

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
FRED DEAN,SHINAULT
RAS #309
5435 N GARLAND AVE STE 140-121, GARLAND, TX 75040

Tenant

๐Ÿข
Monica W. Holvey