๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Cedar Crest Field House
1007 Hutchins Road, Dallas, TX 75203, Dallas, TX, 75203
Construction50%
๐Project Metrics
TDLR #TABS2022008263$1.4M
Project Value
3,914
Square Feet
$361/sqft
Cost/SqFt
7 months
Duration
Registered:Dec 28, 2021
Start:Feb 15, 2022
Target:Sep 18, 2022
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Restroom facilities, locker room, concessions & ticketing for the Cedar Crest Football/Baseball field
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 28, 2021
Construction Start
February 15, 2022
Expected Completion
September 18, 2022