๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Benbrook Relief Elementary School in Ventana
Address TBD, Fort Worth, TX 76126, Fort Worth, TX, 76126
Construction50%
๐Project Metrics
TDLR #TABS2022008270$35.6M
Project Value
120,000
Square Feet
$297/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Dec 28, 2021
Start:Mar 1, 2022
Target:Aug 31, 2023
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New elementary school for Fort Worth ISD.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 28, 2021
Construction Start
March 1, 2022
Expected Completion
August 31, 2023
๐Related Projects
๐คSame Owner
$109.6M totalProperty Owner
๐ค
Fort Worth Independent School District
Contact: Vicki Burris
4 projects ยท $109.6M
3150 McCart Avenue, Fort Worth, Texas 76110
Design Firm
๐๏ธ
Glenn|Partners
4 projects ยท $194.5M
5646 Milton St Suite 426, Dallas, Texas 75206