โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Dr. Sam Joy

3964 State Highway 121 #100, Lewisville, TX 75056, Lewisville, TX, 75056
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022009102
$330K
Project Value
2,500
Square Feet
$132/sqft
Cost/SqFt
4 months
Duration
Registered:Jan 12, 2022
Start:Feb 14, 2022
Target:May 31, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

interior finish out for vet clinic

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 12, 2022
Construction Start
February 14, 2022
Expected Completion
May 31, 2022