๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

IH 30

From: SH 205 To: West of FM 2642, Rockwall, TX 75087, Rockwall, TX, 75087
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022009955
$309K
Project Value
62,000
Square Feet
$5/sqft
Cost/SqFt
4y 1mo
Duration
Registered:Jan 24, 2022
Start:Feb 1, 2023
Target:Feb 1, 2027
Remaining:406 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Reconstruct and widen 4 mainlanes to 6; reconstruct and widen 4 frontage roads to 4/6; construct new and reconstruct existing interchanges; ramp modifications and pedestrian improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 24, 2022
Construction Start
February 1, 2023
Expected Completion
February 1, 2027

Quick Actions

TDLR ID: TABS2022009955

Design Firm

๐Ÿ›๏ธ
Jacobs
4 projects ยท $282.6M
1999 Bryan St., Suite 1200, Dallas, Texas 75201

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201