IAH GATE A20 MODIFICATIONS - PHASE 2
2800 N. Terminal Rd, Houston, TX 77032, Houston, TX, 77032
Completed100%
๐Project Metrics
TDLR #TABS2022010155$1.0M
Project Value
1
Square Feet
$1048.00K/sqft
Cost/SqFt
10 months
Duration
Registered:Jan 26, 2022
Start:Feb 1, 2022
Target:Nov 16, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
CURRENT GATE A20 UTILIZATION IS BY THE MEANS OF GROUND BOARDING THROUGH THE EXISTING SOUTH EXIT DOOR (STAIRWAY #9 ON PLANS) AND FOR ADA, PASSENGERS ARE ESCORTED BY THE HAS CREW VIA THE ELEVATOR IN THE CONCOURSE (ADJACENT TO STAIRWAY #8 ON PLANS)
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 26, 2022
Construction Start
February 1, 2022
Expected Completion
November 16, 2022