🏁Project Closed🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Redemption dental frisco
3535 victory Group Way, Frisco, TX 75304, Frisco, TX, 75304
Completed100%
📊Project Metrics
TDLR #TABS2022013102$60K
Project Value
3,340
Square Feet
$18/sqft
Cost/SqFt
2 months
Duration
Registered:Mar 2, 2022
Start:Mar 7, 2022
Target:Apr 29, 2022
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
repair sheetrock from water damage
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
March 2, 2022
Construction Start
March 7, 2022
Expected Completion
April 29, 2022