📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Urby Dallas Phase 2
1960 Hi Line Dr, Dallas, TX 75207, Dallas, TX, 75207
Construction50%
📊Project Metrics
TDLR #TABS2022016705$99.0M
Project Value
411,592
Square Feet
$241/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Apr 14, 2022
Start:Aug 1, 2022
Target:Nov 11, 2024
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Phase Two of a Three-Phase Apartment Development to include 364 Apartment units in a 27-story high rise tower with attached 1-story retail and lobby structure. Parking for Phase Two is included in a separate 9-tier open garage structure.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
April 14, 2022
Construction Start
August 1, 2022
Expected Completion
November 11, 2024
Property Owner
👤
Urby Dallas Fee Owner, L.P. c/o Ironstate Development, LLC
Contact: Jake Swiggett
50 Washington St, Hoboken, New Jersey 07030