๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Dunbar High School 9th Grade Wing Flooring Replacement

5700 Ramey Ave, Fort Worth, TX 76112, Fort Worth, TX, 76112
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022018283
$300K
Project Value
33,000
Square Feet
$9/sqft
Cost/SqFt
2 months
Duration
Registered:May 4, 2022
Start:Jun 1, 2022
Target:Jul 31, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

The scope of work includes replacing VCT flooring in corridors and classrooms, stairs finishes with stair rubber treads and sealing the existing concrete in the 2 story portion of the school.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 4, 2022
Construction Start
June 1, 2022
Expected Completion
July 31, 2022

Quick Actions

TDLR ID: TABS2022018283

Design Firm

๐Ÿ›๏ธ
VLK Architects Inc
4 projects ยท $60.5M
2821 West 7th St Suite 300, Fort Worth, Texas 76107

Registered Accessibility Specialist

๐Ÿ“‹
BONITA L,ANDERSON
RAS #1087
1816 S FM 51 NO 400-178, DECATUR, TX 76234