โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Bond 2020 Roy Miller High School Renovation

1 Battlin Buc Blvd., Corpus Christi, TX 78408, Corpus Christi, TX, 78408
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022018880
$4.0M
Project Value
120,000
Square Feet
$33/sqft
Cost/SqFt
1y 7mo
Duration
Registered:May 12, 2022
Start:Jun 6, 2022
Target:Dec 31, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Interior renovation of original 3-story school building to include new interior finishes, limited demolition and new walls; Will include limited HVAC, plumbing, electrical work and no exterior wall construction with limited yard drainage work.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 12, 2022
Construction Start
June 6, 2022
Expected Completion
December 31, 2023