๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
US 377
S. of FM 1171 to N. of Crawford Rd, Flower Mound, TX 76226, Flower Mound, TX, 76226
Construction50%
๐Project Metrics
TDLR #TABS2023002785$2.1M
Project Value
250,000
Square Feet
$8/sqft
Cost/SqFt
3y 1mo
Duration
Registered:Oct 10, 2022
Start:Sep 1, 2024
Target:Sep 1, 2027
Remaining:618 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction and widening of US 377 from S of FM 1171 to N of Crawford Rd from 2-ln rural section to 4-ln divided urban section with curbs, raised medians, sidewalks, ped. crossings at signalized intersections and sidewalks adjacent retaining wall
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 10, 2022
Construction Start
September 1, 2024
Expected Completion
September 1, 2027
๐Related Projects
๐คSame Owner
$391.1M total๐๏ธSame Design Firm
$57.4M totalProperty Owner
๐ค
TxDOT District: Dallas
Contact: Travis Campbell
4 projects ยท $391.1M
4777 E. US 80, Mesquite, Texas 75151
Design Firm
๐๏ธ
Jacobs Engineering Group
4 projects ยท $57.4M
1999 Bryan Street, Suite 1200, Dallas, Texas 76006