๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Youth Assembly Room Finish Out

733 Cross St., New Braunfels, TX 78130, New Braunfels, TX, 78130
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023006525
$97K
Project Value
3,600
Square Feet
$27/sqft
Cost/SqFt
2 months
Duration
Registered:Dec 1, 2022
Start:Jan 16, 2023
Target:Mar 31, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Finish-Out Shell Space from 2014 AMC Building Project that will include metal stud framing, DFH, insulation, drywall, tape, finish, paint, electrical (lighting & receptacles), and HVAC (no equipment).

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 1, 2022
Construction Start
January 16, 2023
Expected Completion
March 31, 2023

Quick Actions

TDLR ID: TABS2023006525

Registered Accessibility Specialist

๐Ÿ“‹
ARTHUR J,MORGAN
RAS #1174
1308 COMMON ST # 205-438, NEW BRAUNFELS, TX 78130