AUSTIN PARKWAY ELEMENTARY SCHOOL DRAINAGE IMPROVEMENTS

4400 AUSTIN PARKWAY, Sugar Land, TX 77479, Sugar Land, TX, 77479
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023007675
$800K
Project Value
3,988
Square Feet
$201/sqft
Cost/SqFt
6 months
Duration
Registered:Dec 15, 2022
Start:Jan 9, 2023
Target:Jun 30, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Remove portion of concrete play court and sod and regrade for positive drainage. Add new 48'x80' Pre-Engineered shade structure over new 49'-4"x80'-10" concrete play court w/ 2 basketball goals and new storm drainage.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 15, 2022
Construction Start
January 9, 2023
Expected Completion
June 30, 2023