Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Precinct One - Park Playground Replacement
12301 Sonnier St., Houston, TX 77044, Houston, TX, 77044
Final Inspection85%
๐Project Metrics
TDLR #TABS2023007793$354K
Project Value
12,265
Square Feet
$29/sqft
Cost/SqFt
0 months
Duration
Registered:Dec 18, 2022
Start:Aug 25, 2022
Target:Aug 31, 2022
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Design and installation of playground equipment.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 18, 2022
Construction Start
August 25, 2022
Expected Completion
August 31, 2022
Property Owner
๐ค
Harris County Precinct One
4 projects ยท $15.0M
7901 El Rio St., Houston, Texas 77054